Site Work and Grading Sequence
🔗 Sequence
construction
Site Work and Grading Sequence
Updated Mar 26, 2026
📋 Share Link
Site preparation sequence: 1) Survey/staking, 2) Tree protection/clearing, 3) Erosion controls (SWPPP), 4) Demolition, 5) Rough grading, 6) Underground utilities (storm, sewer, water, gas, electric, telecom), 7) Sub-base preparation, 8) Fine grading, 9) Paving/landscaping.
TAGS
site-work
grading
utilities
earthwork
sequence
DETAILS
phase
BUILD
category
Site — Earthwork
successor
Foundation work
predecessor
Permits, SWPPP, utility locates
critical holds
["Erosion controls in place","Utility locates verified"]
weather dependency
Soil moisture, frost
RELATED KNOWLEDGE
🔗 Sequence
Foundation → Framing Sequence (Hold Point: Foundation Inspection)
Framing cannot begin until foundation inspection passes. Concrete must achieve minimum 75% design strength before loading. Foundation inspection is a hard hold point in every jurisdiction.
🔗 Sequence
Rough MEP → Insulation Sequence (Hold Point: Rough-In Inspection)
Insulation and drywall cannot begin until rough mechanical, electrical, and plumbing inspections pass. All three trades must complete rough-in and be inspected before walls can be closed.
📋 Code
IBC Section 1107 — Accessible Unit and Dwelling Unit Elements
Requires accessible common use elements within individual residential units.
📋 Code
IECC Section 603 — Energy Cost Budget Method
Provides performance-based alternative to prescriptive energy code requirements.
🔗 Sequence
Drywall → Paint/Finishes Sequence
After drywall hung and taped: prime, texture, paint. Flooring after paint (or protect if before). Cabinets after drywall, before countertops. Trim/millwork after paint. Final clean before CO inspection.
📋 Code
NFPA 99 — Health Care Facilities Code
Comprehensive code for safety systems in hospitals and medical facilities.