Structural steel erection follows: 1) Anchor bolt survey and verification, 2) Column erection with temporary bracing, 3) Beam/girder placement, 4) Plumbing and alignment, 5) Connection bolting/welding, 6) Metal deck installation, 7) Shear stud welding, 8) Permanent bracing, 9) Touch-up fireproofing.
TAGS
steelerectionstructuresequencebolting
DETAILS
phase
BUILD
category
Structure — Steel
duration
2-8 weeks typical
successor
Metal deck → concrete slab
predecessor
Foundation complete + anchor bolts verified
critical holds
["Anchor bolt survey","Connection inspection","Fireproofing"]
RELATED KNOWLEDGE
🔗 Sequence
Foundation → Framing Sequence (Hold Point: Foundation Inspection)
Framing cannot begin until foundation inspection passes. Concrete must achieve minimum 75% design strength before loading. Foundation inspection is a hard hold point in every jurisdiction.
🔗 Sequence
Rough MEP → Insulation Sequence (Hold Point: Rough-In Inspection)
Insulation and drywall cannot begin until rough mechanical, electrical, and plumbing inspections pass. All three trades must complete rough-in and be inspected before walls can be closed.
📋 Code
IBC Section 1107 — Accessible Unit and Dwelling Unit Elements
Requires accessible common use elements within individual residential units.
📋 Code
IECC Section 603 — Energy Cost Budget Method
Provides performance-based alternative to prescriptive energy code requirements.
🔗 Sequence
Drywall → Paint/Finishes Sequence
After drywall hung and taped: prime, texture, paint. Flooring after paint (or protect if before). Cabinets after drywall, before countertops. Trim/millwork after paint. Final clean before CO inspection.
📋 Code
NFPA 99 — Health Care Facilities Code
Comprehensive code for safety systems in hospitals and medical facilities.
← Back to Knowledge Garden