Concrete Slab-on-Grade — Pour-in-Place Method

Updated Mar 24, 2026
Standard method for ground-level concrete slabs. Includes subgrade prep, vapor barrier, rebar/mesh, form setting, pour, finish, and cure. Typical crew: 6 workers. Productivity: 40-60 CY/day.

Step-by-step: (1) Compact subgrade to 95% Proctor density. (2) Place 4-6 inches compacted gravel base. (3) Install 10-mil polyethylene vapor barrier, overlapping seams 6 inches. (4) Set edge forms to line and grade — verify with laser level. (5) Place rebar or welded wire reinforcement per structural drawings. Use chairs to maintain proper cover (typically 2 inches from bottom). (6) Pre-pour inspection — hold point. Inspector checks subgrade, vapor barrier, reinforcement placement. (7) Place concrete — order 10% overage. Test slump and air content at truck. (8) Strike off with screed. Bull float. Wait for bleed water to evaporate. (9) Power trowel to desired finish. (10) Apply curing compound or wet cure with burlap and water for 7 days minimum. (11) Cut control joints at 24-48 hours — spacing per ACI 360 (typically 2-3x slab thickness in feet). Quality checkpoints: subgrade compaction test, slump test, air content test, cylinder break tests (3-day, 7-day, 28-day).

TAGS
methodconcreteslab-on-gradepour-in-placefinishingcuring
DETAILS
steps
[{"order":1,"description":"Compact subgrade to 95% Proctor","duration_hrs":4},{"order":2,"description":"Place gravel base and vapor barrier","duration_hrs":3},{"order":3,"description":"Set forms and place reinforcement","duration_hrs":6},{"order":4,"description":"Pre-pour inspection (hold point)","duration_hrs":0.5},{"order":5,"description":"Place and finish concrete","duration_hrs":4},{"order":6,"description":"Cure 7+ days","duration_hrs":0}]
method category
concrete_placement
crew composition
{"foreman":1,"laborers":2,"finishers":3}
equipment needed
["concrete_pump","vibrator","screed","bull_float","power_trowel"]
productivity rate
{"unit":"CY/day","value":50,"crew_size":6}
RELATED KNOWLEDGE
🔧 Method
Wood Wall Framing — Platform Frame Construction
Standard method for framing exterior and interior walls in residential and light commercial construction. Build walls flat on deck, tilt up. 16 or 24 OC stud spacing. Headers over openings.
🔧 Method
Steel Erection Method
Step-by-step procedure for erecting structural steel frames: anchor bolts, columns, beams, connections, plumbing, decking.
🔧 Method
Plumbing Rough-In Method (Residential DWV + Supply)
Procedure for installing drain-waste-vent and water supply piping before walls and ceilings are closed.
🔧 Method
Masonry Wall Construction Method
Step-by-step procedure for building CMU or brick walls: layout, mortar, unit placement, reinforcing, grouting.
🔧 Method
Concrete Formwork Construction Method
Procedure for building and stripping concrete forms: wall forms, column forms, slab forms, and foundations.
🔧 Method
Ceramic/Porcelain Tile Installation Method
Thin-set tile installation on floors and walls: substrate preparation, layout, setting, grouting, and sealing.
← Back to Knowledge Garden