Plumbing Rough-In Method (Residential DWV + Supply)

Updated Mar 25, 2026
Procedure for installing drain-waste-vent and water supply piping before walls and ceilings are closed.

1) Layout: mark fixture locations on plates/floor per plan. Verify clearances. 2) DWV (drain-waste-vent): Start from building drain/sewer connection, work UP. Minimum slopes: 1/4 in/ft for 3 in and smaller, 1/8 in/ft for 4 in and larger. Install main stack (3-4 in), branch drains (1.5-2 in), vent risers (1.5-2 in). Cleanouts at base of stacks, every 100 ft horizontal. 3) Test DWV: air test (5 psi, 15 min) or water test (10 ft head, 15 min). Fix all leaks. 4) Supply: install main water line (3/4-1 in), branch to fixtures. PEX: home-run (manifold) or trunk-and-branch. Copper: solder/ProPress. Hot water line: insulate in unconditioned spaces. PRV (pressure reducing valve) if street pressure >80 psi. 5) Gas: black iron or CSST from meter to appliances. Test: 3 psi for 10 min, soap test all connections. 6) Fixtures rough dimensions: toilet rough 12 in from finished wall, lavatory drain 17-19 in height, shower drain centered. Call for rough inspection before closing walls. CSI 22 10 00.

TAGS
plumbingrough-inDWVwater-supplypipemethod
DETAILS
crew size
2-3
equipment
["pipe cutter","soldering","ProPress","PEX crimper","test gauge"]
RELATED KNOWLEDGE
🔧 Method
Concrete Slab-on-Grade — Pour-in-Place Method
Standard method for ground-level concrete slabs. Includes subgrade prep, vapor barrier, rebar/mesh, form setting, pour, finish, and cure. Typical crew: 6 workers. Productivity: 40-60 CY/day.
🔧 Method
Wood Wall Framing — Platform Frame Construction
Standard method for framing exterior and interior walls in residential and light commercial construction. Build walls flat on deck, tilt up. 16 or 24 OC stud spacing. Headers over openings.
🔧 Method
Steel Erection Method
Step-by-step procedure for erecting structural steel frames: anchor bolts, columns, beams, connections, plumbing, decking.
🔧 Method
Masonry Wall Construction Method
Step-by-step procedure for building CMU or brick walls: layout, mortar, unit placement, reinforcing, grouting.
🔧 Method
Concrete Formwork Construction Method
Procedure for building and stripping concrete forms: wall forms, column forms, slab forms, and foundations.
🔧 Method
Ceramic/Porcelain Tile Installation Method
Thin-set tile installation on floors and walls: substrate preparation, layout, setting, grouting, and sealing.
← Back to Knowledge Garden