Concrete Slab-on-Grade Pour Method

Updated Mar 26, 2026
Complete procedure for placing, finishing, and curing a concrete slab-on-grade.

1) Subgrade prep: compact to 95% modified Proctor, proof roll. Vapor barrier: 10-15 mil poly (ASTM E1745), lapped 6in, sealed. 2) Formwork: 2x4/2x6 lumber or metal, staked at 4ft, verified elevation with laser level. Pour strips for large slabs (max 50-60ft between control joints). 3) Reinforcement: WWR or rebar on chairs (3in clear from bottom, 2in from top for 4in slab with rebar at center). Edge forms for thickened edge. 4) Pre-pour: wet subgrade (not standing water), check weather (no rain, >50F). 5) Pour: place concrete (pump or direct), spread with come-along, strike off with screed (vibrating or manual). Max 90 min from batch to placement. 6) Finish: bull float immediately after screeding, wait for bleed water to absorb, power trowel (wait until thumbprint ~1/4in). Broom finish for exterior, hard trowel for interior. 7) Control joints: saw-cut within 6-18 hrs, 1/4 slab depth, max 15ft spacing. 8) Cure: wet cure, curing compound, or blankets for 7 days minimum.

TAGS
concreteslabpourfinishingcuringmethod
DETAILS
crew size
6-10
equipment
["pump or chute","screed","bull float","power trowel","saw"]
RELATED KNOWLEDGE
🔧 Method
Concrete Slab-on-Grade — Pour-in-Place Method
Standard method for ground-level concrete slabs. Includes subgrade prep, vapor barrier, rebar/mesh, form setting, pour, finish, and cure. Typical crew: 6 workers. Productivity: 40-60 CY/day.
🔧 Method
Wood Wall Framing — Platform Frame Construction
Standard method for framing exterior and interior walls in residential and light commercial construction. Build walls flat on deck, tilt up. 16 or 24 OC stud spacing. Headers over openings.
🔧 Method
Steel Erection Method
Step-by-step procedure for erecting structural steel frames: anchor bolts, columns, beams, connections, plumbing, decking.
🔧 Method
Plumbing Rough-In Method (Residential DWV + Supply)
Procedure for installing drain-waste-vent and water supply piping before walls and ceilings are closed.
🔧 Method
Masonry Wall Construction Method
Step-by-step procedure for building CMU or brick walls: layout, mortar, unit placement, reinforcing, grouting.
🔧 Method
Concrete Formwork Construction Method
Procedure for building and stripping concrete forms: wall forms, column forms, slab forms, and foundations.
← Back to Knowledge Garden