Procedure for rough and finish grading: establishing slopes, swales, and positive drainage away from structures.

1) Survey: establish benchmarks, verify finish floor elevation (FFE), determine drainage patterns. 2) Rough grade: within 0.3ft of design. Equipment: dozer for large areas, skid steer for tight. Minimum slopes: 6in fall in first 10ft from foundation (IRC R401.3), 2% elsewhere. 3) Swales: v-shaped or parabolic, 1% minimum slope longitudinal, lined with grass/rip-rap. 4) Drainage structures: catch basins, French drains (4in perforated HDPE in gravel, filter fabric wrap). Daylight discharge or connect to storm. 5) Compaction: 95% Standard Proctor for structural fill, 90% for landscape areas. Test with nuclear gauge. 6) Finish grade: within ±0.1ft. Topsoil: 4-6in for lawn areas, 12in for planting beds. 7) Erosion control: silt fence, inlet protection, stabilized construction entrance maintained until 70% vegetation established. 8) Inspection: grade verified before foundation pour, before final landscaping.

TAGS
gradingdrainageswalecompactionsiteworkmethod
DETAILS
crew size
2-4
equipment
["dozer","skid-steer","laser-level","nuclear-gauge"]
RELATED KNOWLEDGE
🔧 Method
Concrete Slab-on-Grade — Pour-in-Place Method
Standard method for ground-level concrete slabs. Includes subgrade prep, vapor barrier, rebar/mesh, form setting, pour, finish, and cure. Typical crew: 6 workers. Productivity: 40-60 CY/day.
🔧 Method
Wood Wall Framing — Platform Frame Construction
Standard method for framing exterior and interior walls in residential and light commercial construction. Build walls flat on deck, tilt up. 16 or 24 OC stud spacing. Headers over openings.
🔧 Method
Steel Erection Method
Step-by-step procedure for erecting structural steel frames: anchor bolts, columns, beams, connections, plumbing, decking.
🔧 Method
Plumbing Rough-In Method (Residential DWV + Supply)
Procedure for installing drain-waste-vent and water supply piping before walls and ceilings are closed.
🔧 Method
Masonry Wall Construction Method
Step-by-step procedure for building CMU or brick walls: layout, mortar, unit placement, reinforcing, grouting.
🔧 Method
Concrete Formwork Construction Method
Procedure for building and stripping concrete forms: wall forms, column forms, slab forms, and foundations.
← Back to Knowledge Garden