Rough MEP → Insulation Sequence (Hold Point: Rough-In Inspection)

Updated Mar 24, 2026
Insulation and drywall cannot begin until rough mechanical, electrical, and plumbing inspections pass. All three trades must complete rough-in and be inspected before walls can be closed.

After framing inspection passes, the rough-in phase begins. This requires careful coordination: (1) Plumber installs drain/waste/vent and supply piping, (2) Electrician installs wiring, boxes, and panels, (3) HVAC installer runs ductwork and refrigerant lines, (4) Low-voltage installer runs data/comm/security cabling, (5) Fire protection installer runs sprinkler piping (if required). All trades must coordinate penetrations and routing. Once complete: rough plumbing inspection, rough electrical inspection, rough mechanical inspection (some jurisdictions combine these). Only after ALL rough inspections pass can insulation be installed. After insulation: insulation inspection (energy code compliance). Then drywall can begin.

TAGS
sequencingrough-inmepinspectioninsulationdrywallhold-point
DETAILS
activity
insulation
prerequisites
[{"type":"hard","activity":"rough_plumbing_inspection"},{"type":"hard","activity":"rough_electrical_inspection"},{"type":"hard","activity":"rough_mechanical_inspection"}]
trade conflicts
["electrical and plumbing cannot share same stud bay"]
RELATED KNOWLEDGE
🔗 Sequence
Foundation → Framing Sequence (Hold Point: Foundation Inspection)
Framing cannot begin until foundation inspection passes. Concrete must achieve minimum 75% design strength before loading. Foundation inspection is a hard hold point in every jurisdiction.
🔗 Sequence
Drywall → Paint/Finishes Sequence
After drywall hung and taped: prime, texture, paint. Flooring after paint (or protect if before). Cabinets after drywall, before countertops. Trim/millwork after paint. Final clean before CO inspection.
🔗 Sequence
Sequence: Concrete Pour → Cure → Strip Forms → Backfill
Concrete placement to form stripping sequence with cure times, strength requirements, and hold points.
🔗 Sequence
Sequence: Roof Deck → Underlayment → Flashing → Field Roofing → Ridge/Hip
Complete roofing installation sequence from structural deck to finished weatherproof surface.
🔗 Sequence
Sequence: MEP Underground → Rough-In → Test → Insulate → Close Walls
Mechanical/electrical/plumbing installation sequence from underground to wall closure.
🔗 Sequence
Sequence: Site Clear → Grade → Utilities → Foundation
Site preparation sequence from clearing through foundation construction.
← Back to Knowledge Garden