Sequence: Site Clear → Grade → Utilities → Foundation

Updated Mar 25, 2026
Site preparation sequence from clearing through foundation construction.

Phase 1 — CLEAR: Remove vegetation, trees, structures per plan. Erosion/sediment controls (silt fence, inlet protection) BEFORE disturbance per NPDES/SWPPP. Tree protection fencing for preserved trees. Phase 2 — STRIP/STOCKPILE: Remove topsoil (typically 6-12 in), stockpile for re-use. Phase 3 — ROUGH GRADE: Cut/fill to subgrade elevation. Compact fill in 8-12 in lifts to 95% Standard Proctor (ASTM D698). Proof roll with loaded truck. Geotechnical testing: density tests per plan (nuclear gauge or sand cone). Phase 4 — UTILITIES: Install underground water, sewer, storm, gas, electric, telecom. Trench safety per OSHA Subpart P. Bedding material, compaction around pipes. Pressure test water. Video inspect sewer. HOLD POINT: utility inspection. Phase 5 — FOUNDATION: Excavate to bearing elevation. Verify soil bearing capacity (may require geotech). Forms, rebar, anchor bolts per structural plan. HOLD POINT: footing inspection (before pour). Pour footings. Cure. Foundation walls. Waterproof. Drainage system. Backfill after walls cured + braced/loaded. HOLD POINT: foundation inspection.

TAGS
siteworkgradingutilitiesfoundationexcavationsequence
DETAILS
phases
["clear","strip","rough-grade","utilities","foundation"]
hold points
["erosion control","utility inspection","footing inspection","foundation inspection"]
RELATED KNOWLEDGE
🔗 Sequence
Foundation → Framing Sequence (Hold Point: Foundation Inspection)
Framing cannot begin until foundation inspection passes. Concrete must achieve minimum 75% design strength before loading. Foundation inspection is a hard hold point in every jurisdiction.
🔗 Sequence
Rough MEP → Insulation Sequence (Hold Point: Rough-In Inspection)
Insulation and drywall cannot begin until rough mechanical, electrical, and plumbing inspections pass. All three trades must complete rough-in and be inspected before walls can be closed.
🔗 Sequence
Drywall → Paint/Finishes Sequence
After drywall hung and taped: prime, texture, paint. Flooring after paint (or protect if before). Cabinets after drywall, before countertops. Trim/millwork after paint. Final clean before CO inspection.
🔗 Sequence
Sequence: Concrete Pour → Cure → Strip Forms → Backfill
Concrete placement to form stripping sequence with cure times, strength requirements, and hold points.
🔗 Sequence
Sequence: Roof Deck → Underlayment → Flashing → Field Roofing → Ridge/Hip
Complete roofing installation sequence from structural deck to finished weatherproof surface.
🔗 Sequence
Sequence: MEP Underground → Rough-In → Test → Insulate → Close Walls
Mechanical/electrical/plumbing installation sequence from underground to wall closure.