Sequence: Steel Frame → Metal Deck → Concrete Fill → MEP Rough

Updated Mar 26, 2026
Multi-story steel building sequence from frame erection through composite floor completion.

Phase 1 — STEEL FRAME: erect columns, beams, bracing per erection plan. Plumb and align. Final bolt-up (snug-tight, pretensioned, or slip-critical per connection schedule). HOLD POINT: structural steel inspection (connections, plumb, alignment). Phase 2 — METAL DECK: install composite floor deck (typically 2in or 3in corrugated steel, 20 gauge). Weld puddle welds or mechanically fasten to beams. Shear studs welded through deck to beams (3/4in dia typical). Deck edge pour stops and slab closure pieces. Phase 3 — CONCRETE FILL: place lightweight or normal weight concrete over deck (typically 3.25in above deck ribs for 2hr rating). Welded wire reinforcement or fiber reinforcement. HOLD POINT: deck/stud inspection before pour. Phase 4 — CORE/MEP: core walls, stairs, elevator shafts. MEP rough follows steel frame up the building. Trades sequence: sprinkler → mechanical duct → plumbing → electrical → data.

TAGS
steel-framemetal-deckcompositemulti-storysequence
DETAILS
phases
["steel erection","metal deck","concrete fill","core/MEP"]
hold points
["steel inspection","deck/stud inspection"]
RELATED KNOWLEDGE
🔗 Sequence
Foundation → Framing Sequence (Hold Point: Foundation Inspection)
Framing cannot begin until foundation inspection passes. Concrete must achieve minimum 75% design strength before loading. Foundation inspection is a hard hold point in every jurisdiction.
🔗 Sequence
Rough MEP → Insulation Sequence (Hold Point: Rough-In Inspection)
Insulation and drywall cannot begin until rough mechanical, electrical, and plumbing inspections pass. All three trades must complete rough-in and be inspected before walls can be closed.
🔗 Sequence
Drywall → Paint/Finishes Sequence
After drywall hung and taped: prime, texture, paint. Flooring after paint (or protect if before). Cabinets after drywall, before countertops. Trim/millwork after paint. Final clean before CO inspection.
🔗 Sequence
Sequence: Concrete Pour → Cure → Strip Forms → Backfill
Concrete placement to form stripping sequence with cure times, strength requirements, and hold points.
🔗 Sequence
Sequence: Roof Deck → Underlayment → Flashing → Field Roofing → Ridge/Hip
Complete roofing installation sequence from structural deck to finished weatherproof surface.
🔗 Sequence
Sequence: MEP Underground → Rough-In → Test → Insulate → Close Walls
Mechanical/electrical/plumbing installation sequence from underground to wall closure.